Saturday 21 and Sunday 22 June 2025

Ongoing roadworks from the previous week.

Ongoing roadworks from the previous week.

Report For Week Commencing Monday 23 June 2025

Gellatly Street (car park entrance to Dock Street)    

closed southbound until July 2026 for construction works.

Constitution Road (from its junction with Bell Street to North Marketgait)       

closed until September 2025 for redevelopment of multi‑storey car park and adjoining areas.  

Blinshall Street (Douglas Street to 50 metres south)       

closed until August 2025 for construction works.

Douglas Street (Blinshall Street to Brown Street)       

temporary traffic lights until August 2025 for construction works.      

Rose Lane      

closed to pedestrians (between Rosebank Road and Arthur Street) until Friday 30 June 2025 for ongoing housing development works.

Scottish and Southern Energy Networks Elmwood Cable Renewal Scheme  

temporary traffic lights and road closure from Tuesday 4 March for 19 weeks:

 

  • Charleston Drive (near Elmwood Road) – temporary traffic lights for 2 weeks;

     

  • Ancrum Road (at Peel Street) – temporary traffic lights for 2 weeks; and

     

  • Tullideph Road (City Road to Greenbank Place) – closed westbound for 2 weeks.

Esplanade, Broughty Ferry (Panmure Street to Bridge Street) 

closed for 12 weeks for carriageway resurfacing and improvement works.  Phase 1 - Bridge Street to Barnhill Rock Garden.

Scotland Gas Network King Street Mains Renewal Scheme

road closures from Monday 19 May for 8 weeks:

 

  • King Street (Fort Street to Westfield Road) – closed for 2 weeks; and

 

  • Westfield Road (King Street to Dundee Road) – closed for 3 weeks.

Broughty Ferry Road

temporary traffic lights outside No 54 from Tuesday 17 June until Thursday 26 June for Scottish Water mains repair.

Strathern Road (east of Crawford Place)  

temporary traffic lights from Monday 23 June for 5 days for water connection work.

Abertay Street (at Nursery Road)

temporary traffic lights from Friday 20 June for one week for Envevo work.

Drumgeith Road

closed from Whitfield Drive to Happyhillock Road/Balunie Drive roundabout from Monday 23 June for one week for carriageway resurfacing.

Hilltown (from 235-247 and 273-287)

footway resurfacing (east side) from Monday 23 June for 10 days.  Parking to be suspended during works.

Forth Place/Crescent (between No 327 and No 349)

closed for 5 days from Monday 23 June for footway resurfacing works.

A90 Kingsway (between Strathmartine Road and Old Glamis Road)

closed from Monday 23 June to Wednesday 25 June from 7.30pm to 6.30am for bridge works by Trunk Road Operator.

Old Liff Road

temporary traffic lights until Tuesday 24 June for new footway construction works.  Area affected is Old Liff Road from its junction with Myrekirk Road to its junction with Gourdie Brae.

Perth Road (at Farington Street) 

temporary traffic lights on Tuesday 24 June for BT work.

High Street, Lochee (Bank Street to Methven Street)

closed from 9.00am to midnight on Wednesday 25 June for Scottish Water work.

Blackness Avenue (at Shaftesbury Terrace)

temporary traffic lights from 9.00am to midnight on Wednesday 25 June  for Scottish Water work.

Dock Street (at Whitehall Crescent) 

temporary traffic lights from 9.00am on Wednesday 25 June to 6.00am on Thursday 26 June for Scottish Water work.

Pitkerro Road (near Longhaugh Road) 

temporary traffic lights from 9.00am on  Wednesday 25 June to 9.00am on Thursday 26 June for Scottish Water work

Glamis Road (at Blackness Road)

temporary traffic lights from 9.00am on Wednesday 25 June to 6.00am on Thursday 26 June for Scottish Water work.

Riverside Esplanade

nearside westbound lane closure from 9.00am on Wednesday 25 June to 6.00am on Thursday 26 June for Scottish Water work.

Tannadice Street (at Wolseley Street) 

temporary traffic lights from 9.00am on Thursday 26 June to midnight for Scottish Water work.

St Martin Crescent (9-21 St Martin Crescent)

closed on Thursday 26 June for Scottish Water work.

Forthcoming

Brook Street/Westfield Road/Claypotts Road junction

temporary traffic lights from Monday 30 June until Monday 21 July for SGN gas works.

Blackness Road (at Glenagnes Road)

temporary traffic lights from Monday 30 June for 2 weeks for Scottish Water work.

Milnbank Road (at Polepark Road)

closed from Monday 30 June for 3 days for joint fill/lining works.

Derwent Avenue

closed from Monday 30 June for 3 days for joint fill/lining works.

Byron Street (Milton Street to No 43 Byron Street)

closed from Monday 30 June for 2 weeks for Scottish Water work.

Balgillo Road 

closed from Tuesday 1 July for 3 days for joint fill/lining works.

Dundee Road (at Victoria Road)

temporary traffic lights from Tuesday 1 July to Thursday 3 July for BT work.

Derby Street

closed on Tuesday 1 July for a Gala Day event between 9.00am and 4.00pm.

Old Glamis Road (at Balgowan Avenue)

temporary traffic lights from 9.00am on Wednesday 2 July to 6.00am on Thursday 3 July for Scottish Water work.

Balfied Road

closed from Wednesday 2 July for 3 days for joint fill/lining works.

Constitution Road

closed from Wednesday 2 July for 3 days for joint fill/lining works.

Trottick Mains (at Old Glamis Road)

access/egress prohibited from 9.00am on Wednesday 2 July to 6.00am on Thursday 3 July for Scottish Water work.

Keswick Terrace (No’s 37-49)

closed on Wednesday 2 July for Scottish Water work.

St Martin Avenue (Thoms Close to Gauldie Place)

closed on Wednesday 2 July for Scottish Water work.

Fountainbleau Drive (Afton Way to Pitkerro Drive)

closed from 9.00am on Thursday 3 July to 6.00am on Friday 4 July for Scottish Water work.

Ninewells Avenue

closed from Thursday 3 July for 3 days for joint fill/lining works.

Balunie Drive

closed from Thursday 3 July for 3 days for joint fill/lining works.

Claverhouse Road (at A90 Forfar Road)

prohibition of left turn (northbound) into A90 Forfar Road from 9.00am on Friday 4 July to 6.00am on Saturday 5 July for Scottish Water work.

Lunan Terrace (Broughty Ferry Road to Kinnordy Terrace)

closed from 9.00am on Friday 4 July to 6.00am on Saturday 5 July for Scottish Water work.

Broughty Ferry Road (at Lunan Terrace)

mini contraflow at 9.00am on Friday 4 July to 6.00am on Saturday 5 July for Scottish Water work.

Balmerino Road (Balunie Drive to Balunie Avenue)

closed from Friday 4 July for 10 days for footway slurry sealing.

Strathern Road (at Crawford Place)

temporary traffic lights on Friday 4 July for Scottish Water work.

Whitfield Drive (Whitfield Rise to Drumgeith Road)

closed from 9.00am to midnight on Friday 4 July to for Scottish Water work.

Hilltown Terrace (Arthur Street to Dalfield Court) 

closed from Monday 7 July for 7 days for Scottish Water work.

Forthill Road (Cedar Road to Anton House)

closed from 9.00am on Tuesday 8 July to 6.00am on Wednesday 9 July for Scottish Water work.

Hawkhill (at Hunter Street)

temporary traffic lights from Wednesday 9 July for 2 days for Scottish Water work.

Fintry Road at junction with Finella Place

temporary traffic lights from Wednesday 9 July to Thursday 10 July for ironwork repairs.

Macalpine Road (from Staffa Place to Camperdown Road)

closed from Saturday 12 July for 7 days for carriageway resurfacing.

Camperdown Road (at Macalpine Road)

closed from Saturday 12 July for 3 days for carriageway resurfacing.

Forth Crescent (between No 44 and No 90)

closed for 5 days from Monday 14 July for footway resurfacing works.

Lothian Crescent (Salton Crescent to Whitfield Loan)

closed from Monday 14 July for 4 weeks for sewer connection work.

Scottish and Southern Energy Networks St Fillans Road Cable Renewal Scheme

temporary traffic lights and road closures from Monday 14 July for 18 weeks:

 

  • St Fillans Road, Dundee between Macalpine Road and St Ninian Terrace and each St Fillans Road cul‑de-sac;

 

  • St Giles Terrace, Dundee between St Fillans Road and St Giles Place;

 

  • St Fillans Terrace, Dundee;

 

  • St Giles Place, Dundee;

 

  • Link footpath between no’s 216 and 224 St Fillans Road;

 

  • Link footpath between no’s 99 and 107 St Ninian Terrace; and

 

  • Link footpath between 87 and 95 St Ninian Terrace.

 


Roads - General

Planned road closures and restrictions are necessary to allow for a variety of maintenance work including resurfacing and reconstruction as well as water, sewer, electricity, gas and telecom supply/renewal/maintenance works, etc.

It may be that the Dundee City Council is not responsible for these works.  However we have a duty to inform the public of any major situation which may arise – planned or otherwise – that may affect their ability to move about the city.  We have included here a listing of road closures and major lane closures or restrictions and the contact numbers for the main utility companies in case you have a query on any specific set of roadworks.

Please note the information provided is current as of the Friday prior to the report date and is subject to change at any time.  Any updates after publication on Fridays are indicated in bold.

For further information about this road report e-mail [email protected].  For specific information please phone any of the telephone numbers given below.

Trunk Roads are not the responsibility of the Council but are presently maintained by Amey Transport Infrastructure on behalf of the Scottish Government's Transport Scotland.  Trunk Roads in Dundee consist of:

A90Kingsway West/Kingsway/Forfar Road (north of Kingsway)
A972Kingsway East
A92Greendykes Road / Broughty Ferry Road (at Carolina House)/ East Dock Street/South Marketgait (to Trades Lane)

Amey Transport Infrastructure - Customer Services

0800 083 0084
British Telecom (Openreach)0800 023 2023
Scottish & Southern Energy (Scottish Hydro Electric)0800 300 999
Scottish Water0800 0778 778
Virgin Media (NTL/Telewest)0333 0005 925
Scotland Gas Networks0845 605 6677
Vodafone (C&W Thus)0333 304 0762
Fibrecity Dundee0800 954 2020

Dundee City Council - Report road, pavement & lighting defects

Report It Online


The position of on-going or planned roadworks, anywhere in Scotland, can be accessed on line by clicking on the following link:

Scottish Roadworks Register


The roadworks contained in this report are restricted to major works executed on the roads maintained either by the local Roads Authority, Transport Scotland or the Tay Road Bridge Board. Details on the roads maintained by these organisations can be viewed by clicking on the following link:

List of Public Roads

Discover Dundee Waterfront